Robex remains on track for first gold at Kiniero in Q4
From GlobeNewswire: 2025-06-13 06:28:00
Construction at Robex’s Kiniero Gold Project in Guinea is on schedule and budget, with the first gold pour expected in Q4 2025. The project is LTI free, with all engineering and design work completed. Grade control drilling at the Mansounia pit is ongoing, with SMP works and materials procurement also progressing well.
The project has seen 55,430m drilled and 61,520 samples collected. Structural, mechanical, and piping works have begun, with concrete completion at 95% for the process plant and 32% for the power station. Steel fabrication, field tank structures, and the tailings storage facility are also progressing as planned.
Robex Resources CEO, Matthew Wilcox, expressed satisfaction with the project’s progress, highlighting the completion of the Initial Public Offer and a successful ASX listing. The company is focused on meeting its milestones and targets, with ongoing work including grade control drilling at the Sabali pit and signing contracts for mining and drill and blast services.
Next steps for the Kiniero project include completing final concrete pours, tailings storage dam lining, and commencing mill installation and steelwork erection. The company aims to finalize contracts for various services, procure necessary spares, and continue advancing construction activities to meet the Q4 2025 gold production target.
Read more at GlobeNewswire: Robex remains on track for first gold at Kiniero in Q4