Paladin Energy Ltd provides FY2026 guidance for the Langer Heinrich Mine, focusing on operational ramp-up and uranium price sensitivities. The LHM is expected to ramp up mining operations throughout FY2026, with full operations planned for FY2027. The company also plans to provide annual guidance for FY2027 in July 2026. The LHM commenced FY2026 with stockpiled ore and mining fleet operations, with mining activities concentrated in the G-pit area. Processing plant performance improvements from FY2025 are expected to continue in FY2026. Sales volumes and pricing are projected to vary quarter on quarter. Realised uranium price sensitivities for FY2026 are based on a range of spot price assumptions.

Read more at GlobeNewswire: Langer Heinrich Mine FY2026 Guidance