Robex Resources Inc. reports strong progress on its Nampala Gold Mine in Mali and the Kiniero Gold Project in Guinea. The company raised C$148.2M through accelerated warrants, amended a $130 million facility with Sprott, and commenced mining at Kiniero. Nampala produced 9,774 ounces of gold in September 2025, with a year-to-date total of 34,401oz at an AISC of C$2,555/oz.
Robex continues to advance the Kiniero Gold Project, with mining operations starting on both day and night shifts. The project remains on track for its first gold pour in Q4 2025. Major construction milestones have been achieved, including completion of the process plant and power station concrete work. The SAG mill assembly is complete, and the leaching circuit construction is ahead of schedule.
Robex’s Nampala Gold Operation in Mali produced 9,774 ounces of gold in the September 2025 quarter, with a year-to-date total of 34,401 ounces. The AISC was reported at C$2,555 per ounce. The operation remains Lost Time Injury free, with strong environmental and safety performance recorded during the quarter.
Exploration and development programs continue at both the Kiniero Gold Project in Guinea and the Nampala Gold Operation in Mali. Key appointments and drilling programs are underway to expand resources and improve ore body understanding. The company’s community and social responsibility initiatives remain a priority, with various projects supporting education, healthcare, and community development in the regions where Robex operates.
Robex maintains a US$130 million senior secured facility with Sprott and recently amended the agreement to provide enhanced funding flexibility. The company’s capital structure was updated with an increase in issued capital and successful warrant exercises. Robex remains focused on achieving its full-year production guidance for the Nampala Gold Operation, with sustaining capital expenditure forecasted between C$30-34 million.
Read more at GlobeNewswire: September 2025 Quarterly Activities Report